Wednesday, May 19, 2010

Shillman House Chronicles: Entry #12


  • Wood framing continues for Shillman's northeast wing! The lull is unloading floor trusses for the second floor.
  • The southeast wing foundations and block stair walls are complete!  The excavator is preparing for underground plumbing. 

Monday, May 3, 2010

Shillman House Chronicles: Entry #11

  • Shillman House's elevator shaft has been completed and now the masonry staging is set up to build the growing stairwell in the northeast wing.  The first floor concrete has been placed in the northeast wing. The walls of the first floor are going up quickly!
  • The pre-fab first floor walls are going up one section at a time.  You can see a team placing a section of an exterior wall in place.



 