Tuesday, June 29, 2010

Shillman House Chronicles: Entry #15


Shillman House is really taking shape!
  • WOW!  The very first window is being installed.  It's for a staff office in the northeast wing.  
  • The concrete trucks are here to create the last slab placement, completing the major portion of concrete in the buildings!  The roof is nearly complete on the northeast wing, while the third floor walls are going up in the northwest wing. 

Wednesday, June 16, 2010

Shillman House Chronicles: Entry #14



  • The action on 49 Edmands Road continues!  The 40 ton crane in the top photo is hoisting a roof truss onto the northeast wing.
  • The southeast wing of the building will soon take shape, as marked by the slab on grade in the forefront of the bottom photo.  Beyond the future South Courtyard, the first floor wall panels are  being installed in the northwest wing.  Meanwhile, the northeast wing is now up to four floors and the new roof trusses are hidden behind the elevator shaft.  What progress!!

Thursday, June 3, 2010

Shillman House Chronicles: Entry #13



  • Members of JCHE's Real Estate Development Committee gathered on May 14 with our Site Super to check on the progress of Shillman House.  The supporting walls of the 2nd floor in the northeast wing are nearly completed and the drilling of the ninth geothermal well is in progress.  Just one more well to go!

  • Can you believe it?  A first floor corner apartment is taking shape,  and our Committee members are checking it out!  After all the hard work to make Shillman House a reality, it's wonderful to find ourselves surrounded by walls and a ceiling!  
 