Friday, March 26, 2010
Shillman House Chronicles: Entry #7
Workers are busy removing the wall forms from the northeast foundation walls. The reinforced concrete supporting walls are now up.
Blasting of ledge is continuing in the future northwest parking lot. All blasting is being supervised by the Framingham Fire Department. The broken up ledge material is being hauled off of the site.