Workers have begun the installation of waterproofing and rigid insulation to the exterior of the foundation walls of the northeast wing. Shillman House is looking pretty in pink!!

Meanwhile, in the northwest wing, formwork and rebars (reinforced bars) for the basement concrete walls are being installed. There has been so much progress this week!
     